Alpha 1 Progress Report

14 Nov 2008 Southampton, UK

ALPHA 1 (NOV08) - image 2Today, Lucite International's new Alpha 1 plant in Singapore has achieved its first milestone producing more than 1000 metric tonnes of in-specification product. Nick Cordingley, Lucite International Singapore General Manager said: 'The plant continues to run very steadily at the planned 50,000 metric tonnes per year rate and will be held at this rate whilst the customer approval stage is completed. Samples for customer evaluation are being sent out on November 19 to start this process."